Project Description
The currrent district office and training facility located on Airport Road, is at the end of life cycle requiring increased maintenance costs.Project Location
25490 Airport Rd, Punta Gorda, FL 33950Project Impacts
Additional work was conducted with the building pad fill material due to high moisture content. All testing is completed and passed inspection.Latest Updates
The foundation was poured on April 4, 2024. The metal door frames have been installed, start of the CMU block walls has started.
Budget
Phase | Cost |
---|---|
Design | $1,000,000 |
Construction | $8,300,000 |
Total Budget | $9,300,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/11/2021 | 08/15/2022 | 03/17/2022 |
Design Development | 08/15/2022 | 04/13/2023 | 04/14/2023 |
Construction | 10/04/2023 | 06/17/2025 | |
Turnover & Closeout | 06/17/2025 | 07/17/2025 |
Project Phase
Construction
Last Updated
04/10/2024
Project Manager
Gary Burdahl
Public Relations
Brian Gleason
Email Public Relations
Project Number
c892102
Sponsor Department
CCSO
Design Engineer/Architect
Schenkel and Shultz Inc.
Construction Contractor
Wharton-Smith Inc.